Nearly ready for gyprock …

Hi all,

Over the last few weeks I have been busy downstairs. The remainder of the timber wall frames have been completed, along with sarking installed behind the new section of timber frames on the retaining wall. The gyprock got delivered this afternoon.

Today I installed the insulation batts in this same section. This is the only area where I will install the insulation as the rest of the walls are against the outside brick walls, and I don’t think insulation will be needed.  Here are some shots before and after the installation of the batts.

Will do another update next week when the gyprock goes up.

Cheers,

Ian

Advertisements

Posted on December 15, 2010, in Room Construction and tagged . Bookmark the permalink. Leave a comment.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: